Plug-in solar DNO notification · 2026 GUIDE

Do you need to notify your DNO about plug-in solar?

Understand the Great Britain network-notification route for plug-in solar, G98, DNO identification and why the network step still matters for an 800VA device.

Updated 3 September 2026 · Great Britain unless stated otherwise
Quick answer

Plug-in solar is now a real Great Britain route, but suitability depends on the complete product, your property, electrical installation, mounting location, permissions and network requirements. Use the checks below before buying.

Plug-in solar still connects generation to the electricity network

Even though the equipment connects through a standard UK socket, it operates in parallel with the public low-voltage network. That is why the DESNZ specification explicitly requires compliance with the relevant G98 network conditions.

What is a DNO?

A Distribution Network Operator runs the regional electricity distribution network serving your property. It is different from the electricity supplier that sends your bill.

Why G98 matters

Engineering Recommendation G98 sets connection requirements for fully type-tested small-scale generation. The plug-in solar specification says G98 applies in Great Britain and notes separate arrangements for Northern Ireland.

One device per household

The specification allows one device per final circuit from an electrical-product perspective, but states that the current GB network requirement restricts this to one plug-in solar device per household unless G98 is amended.

Keep a record

Keep the product model, inverter details, serial numbers, installation address and any DNO acknowledgement/reference with the property record. This is one of the reasons Solixir stores a post-sale installation record.

Check your actual property

Plug in Solar Ready combines your address, property questions, panel area, consumer-unit and socket evidence into one guided pre-screen.